R
Richard.Natividad
Hi,
I have created a view in View Resource Assignments to list all my
resources with task assignments on server. In it I pull the Start and
Finish. This view is an excellent way of showing the Start and Finish
dates of resources on the project as you can use the Summary level of
each resource.
However, there is a problem I have noted, If a resource has deleted
tasks on a date greater than actually specified in the workplan. The
roll off date shows the Deleted Task Finish date instead as it is the
greater value.
My question is:
Is there a way in PWA to filter out Deleted Tasks so that do not
factor in the Start and Finish Dates for a resource? I cannot see an
option to filter out deleted tasks?
Regards,
Richard Natividad
I have created a view in View Resource Assignments to list all my
resources with task assignments on server. In it I pull the Start and
Finish. This view is an excellent way of showing the Start and Finish
dates of resources on the project as you can use the Summary level of
each resource.
However, there is a problem I have noted, If a resource has deleted
tasks on a date greater than actually specified in the workplan. The
roll off date shows the Deleted Task Finish date instead as it is the
greater value.
My question is:
Is there a way in PWA to filter out Deleted Tasks so that do not
factor in the Start and Finish Dates for a resource? I cannot see an
option to filter out deleted tasks?
Regards,
Richard Natividad