T
trevorbee
We have had several cases where a resource has been complety removed from a
project plan (i.e. the resource has been deleted from the Resource Sheet and
any tasks to which they were assigned ) - yet the project continues to be
displayed in the resource's Project Centre view. This after the changed plan
has been saved and re-published. Can anyone suggest why this is happening and
how to overcome it please ?
project plan (i.e. the resource has been deleted from the Resource Sheet and
any tasks to which they were assigned ) - yet the project continues to be
displayed in the resource's Project Centre view. This after the changed plan
has been saved and re-published. Can anyone suggest why this is happening and
how to overcome it please ?