Mike Kleiman
I have a task that has 4 people allocated at 25% each. Planned work is 100
hours for each resource and they have all tracked 25 hours of actual work on
the task. Resource-a got moved to a special assignment on another project and
needs to be removed from this task. I want to retain resource-a's actuals and
have the remaining planned work redistributed to the other three resources at
33% each. In general, how should this be done?
Thanks
Mike Kleiman