We have a multi-year project tracked in EVM by an annual perspective. For
the contract proposal we needed to show activities throughout the life of the
project. However, we now need to slice all tasks and resources past a
specific date. I do not know of any Project command which will do this
automatically. Does anybody have a macro that can do this?
Thanks. RC