W
Wegz
Hi, I have an ongoing project with a recurrent task every week. That
task has 4 resources assigned to it. One of the resources no longer
works for that team but has work already recorded in the first 4
recurrent tasks.
What is the best way to remove that resource from the project so they
no longer see / can enter against that project but still keep their
completed work in the database for recording purposes?
Thanks for any info.
Matt
task has 4 resources assigned to it. One of the resources no longer
works for that team but has work already recorded in the first 4
recurrent tasks.
What is the best way to remove that resource from the project so they
no longer see / can enter against that project but still keep their
completed work in the database for recording purposes?
Thanks for any info.
Matt