J
Jeff
I have MS Project 2002 std and running project server 2002
successfully. I have a couple of resources that no longer
work for the company and have completed tasks, but never
updated Project Web Access. So, I went into the actual
mpp file (as the PM) and marked the tasks 100% complete
using "tools / tracking / update task". The actual MS
Project file shows the tasks and the project 100%
complete, however when I log onto PWA and
select "Resources" from the menu, it shows the tasks for
those resources still at 0% and 33% respectively. These
resources have been removed from the network by the IT
admin, so nobody can log onto PWA using their accounts.
If I click on "Projects" in PWA, and select the project I
am concerned with, the tasks show that they are
completed. How can I update the "Resources" view to show
these tasks as complete? I have tried to see if I
could "hide" the tasks, but that option is not there under
this view. HELP!
Jeff
successfully. I have a couple of resources that no longer
work for the company and have completed tasks, but never
updated Project Web Access. So, I went into the actual
mpp file (as the PM) and marked the tasks 100% complete
using "tools / tracking / update task". The actual MS
Project file shows the tasks and the project 100%
complete, however when I log onto PWA and
select "Resources" from the menu, it shows the tasks for
those resources still at 0% and 33% respectively. These
resources have been removed from the network by the IT
admin, so nobody can log onto PWA using their accounts.
If I click on "Projects" in PWA, and select the project I
am concerned with, the tasks show that they are
completed. How can I update the "Resources" view to show
these tasks as complete? I have tried to see if I
could "hide" the tasks, but that option is not there under
this view. HELP!
Jeff