Rename column and change date format (dd/mm/yy)

S

Sharin

Hi,

How can I change the current date format for Start and Finish column from
dd/mm/yyyy to dd/mm/yy ?

And how can I change the column name like Actual Start to ActStart?

Thanks
Sharin
(e-mail address removed)
 
M

Manmeet Chaudhari

Hi,
To change the date format
tools-options-view-date format

To change the heading
Insert-column-in the title write the required heading

Hope this helps


Thanks and Regards
Manmeet Chaudhari
 
S

Sharin

Hi,

Thanks for the reply.
It is my fault that I did not write it clearly.

But my question is on the PWA (project web access)
I am wondering if its possible to make these changes.

Thanks again
 
E

Engelbert

No it isn't !

That's to change to things like MM/DD/YY and YY/MM/DD.

Sorry, I should have read your message better.

Aren't these just date alternatives on the server where you are running WSS
and nothing to do with WSS / PWA ?

Engelbert
 
S

Sharin

Thats what I thought. To change the date setting in the server.
Since I could not find any where in PWA to change the format.
 
M

Mike

Sharin

PWA date formats are controlled by client Region and language options
in the operating system

Mike
 
S

Sharin

Thanks Mike.

Had made the change, but did not take effect though.
I'll try and restart the server this evening.

Regards
Sharin
 
S

Sharin

I have restarted the sever but alas the date is still in dd/mm/yyyy format.
I had change the short date and long date to display dd/mmm/yy

BTW, the Project Web is installed on a MS 2003 Server.

Thanks
 
M

Mike

Sharin

The format is determined by the client windows setting not the server.

regards

Mike
 