R
Ryan
Hi All,
I need to change the names for all baseline fields to projected fields, for
example:
Baseline Finish becomes Projected Finish
Baseline Duration -> Projected Duration
Baseline Cost -> Projected Cost
Etc.
I tried creating a Custom Date (Date1) with the formula [Baseline Finish],
but this populates the field with NA instead of a date.
The only way I've been able to get this to work is by saving an Interim plan
and renaming the Finish and Start fields, but this is not ideal because:
1) The reference manually I'm using says to not use Interim plans anymore.
2) It doesn't address baseline cost, etc.
How should I do this?
Thanks for any help,
Ryan
I need to change the names for all baseline fields to projected fields, for
example:
Baseline Finish becomes Projected Finish
Baseline Duration -> Projected Duration
Baseline Cost -> Projected Cost
Etc.
I tried creating a Custom Date (Date1) with the formula [Baseline Finish],
but this populates the field with NA instead of a date.
The only way I've been able to get this to work is by saving an Interim plan
and renaming the Finish and Start fields, but this is not ideal because:
1) The reference manually I'm using says to not use Interim plans anymore.
2) It doesn't address baseline cost, etc.
How should I do this?
Thanks for any help,
Ryan