Rob:
You can, however, rename an enterprise field and reference the built-in
field.
--
Gary L. Chefetz, MVP
"We wrote the books on Project Server"
http://www.msprojectexperts.com
For Project Server FAQs visit
http://www.projectserverexperts.com
For Project FAQs visit
http://www.mvps.org/project
-
Rob Stewart said:
I hear ya Earl,
Although I have brought these points up (There's no calculating SPI without
'cost');
The client wishes not to have any cost data associated in Project Server.
Here's their terminology.
ETC (Estimate Till Completion)= Remaining work, in hours
EAC (Estimate At Completion)= Work
Budget= Baseline Work
%Productivity-Earn/Burn= (ETC from last week - Current ETC)/ Current Actual
Hours
Again,
I hear you, and I do understand the discrepancy between established PMBOK
methodologies, and what I have been asked to do.
I guess we can chalk this up as an example of Project's easy customization
and outstanding flexibility to meet the needs of a dynamic corporate
environment. ;-)
-RS
that I'm the definitive source for such things, but that's to the best of my
knowledge.you're talking about here? Based on my studies of project management and
supported by the MSP help files, remaining work and ETC (EAC is the standard
acronym) are not equivalent. In fact, they're completely different.
Remaining work is a measure of time and EAC is a measure of cost.not EAC!" I would caution against using a term so similar for something so
different. Anyone in your organization that knows the standard project
management terminology is surely to be confused. And those that don't know
the standard terminology will be led to a false understanding. Then, when
they do pursue that PMI certification they'll probably get pretty cranky
about this apparent dichotomy.expressed as a cost. Examples include the Actual Cost and Fixed Cost fields.
The maximum value allowed in this field is 999,999,999,999.99.)determined by Project based on information in other fields. Project may
recalculate the value automatically or when you specify, depending on your
choice of calculation settings.)total cost of a task based on performance up to the status date. EAC is also
called forecast at completion (FAC).EAC is the same as scheduled cost, which is the total work value multiplied
by the resource cost rate. As actual work or actual cost is reported on the
task, Microsoft Office Project 2003 calculates EAC according to this
formula.the expected total cost for the task, based on performance up to the status
date.but I thought it was worth pointing out so you might be able to head off the
use of confusing terminology in your project management and project server
practices. Good luck.