K
knowthediff
What is the best way to implement a set of re-occurring tasks in MS
Project. For example, I have a Pilot and a Production stage. Both
stages will have a set of tasks that are identicla (e.g. Puchase
hardware, install hard ware, install software). Do I have to
duplicate the tasks or is there a way to set up a task so that it
occurs in both stages?
I know you can have subprojects and include/import them into the main
project so I guess I could try to do that twice, but I may want to
exclude certain tasks in the production stage and this method would
not work.
Thx,
-J
Project. For example, I have a Pilot and a Production stage. Both
stages will have a set of tasks that are identicla (e.g. Puchase
hardware, install hard ware, install software). Do I have to
duplicate the tasks or is there a way to set up a task so that it
occurs in both stages?
I know you can have subprojects and include/import them into the main
project so I guess I could try to do that twice, but I may want to
exclude certain tasks in the production stage and this method would
not work.
Thx,
-J