Reoccuring Tasks

J

JS

I have set up a monthly reoccuring task that I would like
to have on the 5th working day of each month.

I can get tasks to reoccur on the fifth day of the month;
I can get them to not fall on weekends, but I cannot get
them to not count a weekend day as one of the 5 days.

Any ideas?
 
M

Mike Glen

Hi JS,

Welcome to this Microsoft Project newsgroup :)

You will have to create a new calendar (or use the 24 hour calendar) to
"release" the week-ends for work. Then apply that callendar to the
recurring task in the Recurring Task dialog.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 