Hi,
is there a way to replace the Standard Calendar in the Enterprise Global.
Background: I have restored the Enterprise Global from a different server.
This Enterprise Global hat a calendar "standard" with 7 h a day. When I
change the default working time to 8 h, every day is marked as changed.
How can I change this to standard 8 h? 8-12am and 1-5pm ?
Thanks for any advice in advance
Pete
is there a way to replace the Standard Calendar in the Enterprise Global.
Background: I have restored the Enterprise Global from a different server.
This Enterprise Global hat a calendar "standard" with 7 h a day. When I
change the default working time to 8 h, every day is marked as changed.
How can I change this to standard 8 h? 8-12am and 1-5pm ?
Thanks for any advice in advance