Hi Shawn,
Welcome to this Microsoft Project newsgroup
Yes. Filter the Gantt view for tasks (Project/Filtered For ()/Using
Resource... and select all the tasks. Then click the Assign resources
button on the Standard toolbar (the double headed icon) and in the Assign
Resources dialog select the leaving resource and click the Replace... button
and chose your new resource.
FAQs, companion products and other useful Project information can be seen at
this web address: <
http://www.mvps.org/project/>
Hope this helps - please let us know how you get on
Mike Glen
MS Project MVP
Shawn said:
Is there a way to 'globally' replace a resouce? For example, if I have
resource "Ted" assigned to 2000 tasks, and i want them all to be replaced
with resource "Jim", is there a one step solution or do I have to manually
reassign each task? Thanks in advance.