J
jem
I have a PM that has been using Project Standard. He has a schedule with
1500 tasks and many resources. Actuals have been posted to the schedule
(manually). He would like to begin using Project Pro/Server. Is there an
easy way to replace all of his local resources with enterprise resources? I
know you can use the Assign Resources option and replace, but that is one
task, one resource at a time. That would take a tremendous amount of time.
Any other options?
Thanks.
jem
1500 tasks and many resources. Actuals have been posted to the schedule
(manually). He would like to begin using Project Pro/Server. Is there an
easy way to replace all of his local resources with enterprise resources? I
know you can use the Assign Resources option and replace, but that is one
task, one resource at a time. That would take a tremendous amount of time.
Any other options?
Thanks.
jem