G
Greg
Hi All:
I'm using Project 2000. Can anyone explain how I replace
resources (that is, reassign tasks from one resource to
another) in all tasks assigned to a particular resource
within projects linked through a resource pool? I want to
explore what effect losing a resource and burdening
remaining workers has on the schedules. (It is easy to do
it one task at a time with assign resources button, but
that would take me a few hours.) One way that may work, in
the resource pool resource sheet view, I can copy a name
and paste it over the resource being eliminated,and change
the max work units to 50% for each duplicate entry. That
gives all assignments to a remaining person, as I intend.
But is this a good way to do this? It doesn't feel right.
Thanks
I'm using Project 2000. Can anyone explain how I replace
resources (that is, reassign tasks from one resource to
another) in all tasks assigned to a particular resource
within projects linked through a resource pool? I want to
explore what effect losing a resource and burdening
remaining workers has on the schedules. (It is easy to do
it one task at a time with assign resources button, but
that would take me a few hours.) One way that may work, in
the resource pool resource sheet view, I can copy a name
and paste it over the resource being eliminated,and change
the max work units to 50% for each duplicate entry. That
gives all assignments to a remaining person, as I intend.
But is this a good way to do this? It doesn't feel right.
Thanks