Replacing resources with actuals reported

A

Andre

I'm trying to import a project to project server. The project already
has actuals reported for the resources. I want to replace the local
resources with the corresponding enterprise resource, but that isn't
possible, due to the fact that the local resource already has actuals
reported. Is there another way of accomplishing this, without having to
re-enter the actuals?

André
 
D

Dale Howard [MVP]

Andre --

If you import the project using using the Import Projects wizard (click
Tools - Enterprise Options - Import Project to Enterprise), the resources
page allows you to match the local resources with enterprise resources. The
wizard will transfer the actuals from the local resources to the enterprise
resources. Hope this helps.




I'm trying to import a project to project server. The project already
has actuals reported for the resources. I want to replace the local
resources with the corresponding enterprise resource, but that isn't
possible, due to the fact that the local resource already has actuals
reported. Is there another way of accomplishing this, without having to
re-enter the actuals?

André
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top