In Project Std 2003 I have a consolidated project for 3 managers, each with
about a dozen projects. What I did was create a summary task for each manager
and then inserted each of their projects below their summary task. I have
also made sure that in the properties of each of their projects, I have their
name as the Manager. Is there any way I can do more with the Manager document
property other than inserting it into the header or footer. For example,
could I generate a report of all projects with overdue tasks, grouped by the
Manager? Thanks.
 
C

Catfish Hunter

First - I would use one of the 30 tect fields to put each managers name in.
Second - Look at the filter in Projects that's already set up for overdue
task and make a copy of it. (Project>Filter>More Filters>Copy) Add Text 1 -
equals - manger xx to the filter. Do this for all managers and you can also
add a view for each if they want differant columns. Good Luck
 