Report of Incomplete Tasks within a Time Period

J

JMcBeth

On our software development project, I need to produce a list of tasks for
each team member for the next milestone (build). I attempted to create this
report by filtering out all completed tasks and then producing a "Who does
what" report with a date range. Unfortunately, the completed tasks are still
appearing in the report. What am I doing wrong?

It would seem to me that a report of all incomplete tasks by resource should
be a standard report. Is there one that I am missing?

Thanks in advnace for any help.
 
J

JackD

Keep working at it. Take a look at the custom reports. I'm pretty sure there
is a place where you can set the filter to use. Filtering the tasks on
screen is not enough. You need to set the filter in the report.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top