Steph
How do I get the resource over allocations to work by week rather than by day?
We are only interested in over allocations if the resource is overallocated
for the whole week but it is highlighting resources in red if they are over
allocated for a single day even if over-all they are actually doing less
hours than they are able to for the whole week.
Thanks,
Steph