Report the total number of Work hours in a calendar quarter

K

Kathy Vehorn

I have a pretty complex schedule with many tasks, subtasks, and resources.
The tasks overlap multiple quarters. I need to generate a report which
calculates the number of work hours within a calendar quarter. Any
suggestions?

Thanx! Kathy
 
G

Gérard Ducouret

Hello Kathy,

Use the Task Usage view : View / Task Usage (or the Resource Usage)
Change the timescale : Format / Timescale...
Set the Bottom Tier to Quarters.

Hope this helps,

Gérard Ducouret
 
G

Gérard Ducouret

PS : Before setting the Bottom Tier to Quarters, you have to set the Middle
Tier to Year, or anything greater than the Bottom Tier unit. Bottom Tier
unit needs to be smaller than Middle Tier unit.

Gérard Ducouret
 
K

Kathy Vehorn

Thank you Gerard. That does the trick!

Gérard Ducouret said:
PS : Before setting the Bottom Tier to Quarters, you have to set the Middle
Tier to Year, or anything greater than the Bottom Tier unit. Bottom Tier
unit needs to be smaller than Middle Tier unit.

Gérard Ducouret
 
K

Kathy Vehorn

One more question for you - Now that I can see exactly what I want on the
screen, (Multiple rows, each with summary task name and number of hours of
work per quarter) how can I export this view to excel?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question