Carl --
I'm not sure this solution meets your reporting needs, but you might give it
a try:
1. Open the project in question
2. Click View - Reports
3. Double-click the Workload reports
4. Double-click the Task Usage report
5. Click the Print button
6. In the Print dialog, select the desired date range in the Timescale
section
7. Click OK to print or Print Preview to preview the results
The Print dialog is one way of date restricting the printing of Views that
contain either the Gantt Chart or the timephased grid, or for date
restricting Reports that are Crosstab reports, of which the Task Usage
report is one. Hope this helps.