Reporting Across Projects

R

RQ

2007 version

We have several projects now on Project Server and the users are interested
in seeing reporting across projects. The project plans are all from the same
template and track the same set of activities. One report we want to create
is a report or view that shows every project and % Complete on milestones
within the plan.

If I create a view in Project Center - I cannot see more then just a one
line summary of each project plan. The users do not want to have to drill
into each project seperately to see this information in Project Details.
Am I missing something in creating a view in Project Center that shows each
project on one page with more then just one summary line?

The next thought was to use the Data Analysis tool but I have read and seen
that it does not contain % complete.

What is the suggested way to get reports out of Project Server across
projects for things like % complete on major milestones

Thanks
RQ
 
P

Paul Conroy

SQL Reporting Services provides the flexibility to produce the detailed
reports you require.

There are some samples available in the SDK (report pack).
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top