reporting hours in a to-do list

A

Artur Rodrigues

Hi,

I have configured my project server web access, option: "Specify the
default method for reporting progress on tasks" to Hours of work done per
day or per week. However, when I create a to-do list my resources have to
report their hours in to-do list in %complete.



How can I set up my to-do list to permit report in hour of work done?


TIA
Artur Rodrigues
 
S

Sarah

Artur,

Why are you using a To-Do list? It would probably be easier to have
your resources use their Timesheet Views to report time. They can set
up the view the way they want to see it, and report time on a daily
basis.

Sarah
 