B
bushie_40
Hi,
We are using Server 2003 and have managed time periods and timesheets
setup. When we assign tasks to a user it has a planned # of hours
allocation and users log time against plan.
The problem we are having are the cases where they completed the task
but it took them less time then planned - it will only show partially
completed. We'd like a way to log time but also check off the task as
completed when it is done. Same problem if there is a task that takes
longer than expected, they will hit 100% and not be able to log more
time.
I'm sure there is an option to solve this?
Thanks,
Paul
We are using Server 2003 and have managed time periods and timesheets
setup. When we assign tasks to a user it has a planned # of hours
allocation and users log time against plan.
The problem we are having are the cases where they completed the task
but it took them less time then planned - it will only show partially
completed. We'd like a way to log time but also check off the task as
completed when it is done. Same problem if there is a task that takes
longer than expected, they will hit 100% and not be able to log more
time.
I'm sure there is an option to solve this?
Thanks,
Paul