D
Dominic Moss
I am looking for some guidance on reporting resource non-availability due to
time booked off:
Whilst Administrative Projects can provide a useful means to capture
non-project time to my mind they are not much use when it comes to trying to
model the impact of resources holiday/vacation booked time off work in
advance. I advocate editing resource availability to show a window of time
being unavailable when a resource has booked time off. The advantage of this
allied to "premature baselining" is that reduced resource availability and
its likely impact on projects can be assessed at an early stage. Once a
resource had taken time off this can be updated in an Administrative
project.
What I would like to be able to do is to produce a report that "counts" the
number of non-working days each resource has in a defined window of time -
this would obviously have to exclude weekends where they are non-working
time by default in the resource base calendar.
Looking at the Resource Usage view a resource can either have work and
remaining availability, work and overallocation or no work and no remaining
availability - the last being periods when nonworking time has been defined
for individual resources.
Does anyone on the newsgroup have experience in producing this kind of
report using SQL and displaying the results in a web view?
--
Dominic Moss
www.projectability.co.uk
Helping people achieve more with Microsoft Project
Tel +44 8707 303 400
Fax +44 8707 303 500
time booked off:
Whilst Administrative Projects can provide a useful means to capture
non-project time to my mind they are not much use when it comes to trying to
model the impact of resources holiday/vacation booked time off work in
advance. I advocate editing resource availability to show a window of time
being unavailable when a resource has booked time off. The advantage of this
allied to "premature baselining" is that reduced resource availability and
its likely impact on projects can be assessed at an early stage. Once a
resource had taken time off this can be updated in an Administrative
project.
What I would like to be able to do is to produce a report that "counts" the
number of non-working days each resource has in a defined window of time -
this would obviously have to exclude weekends where they are non-working
time by default in the resource base calendar.
Looking at the Resource Usage view a resource can either have work and
remaining availability, work and overallocation or no work and no remaining
availability - the last being periods when nonworking time has been defined
for individual resources.
Does anyone on the newsgroup have experience in producing this kind of
report using SQL and displaying the results in a web view?
--
Dominic Moss
www.projectability.co.uk
Helping people achieve more with Microsoft Project
Tel +44 8707 303 400
Fax +44 8707 303 500