Reporting on % resource unit allocations across multiple tasks (MSP2002)

A

Adrian

Hi

I am trying to create a report in %(units) for multiple
resources across multiple task and projects. Any hints??
 
G

Gérard Ducouret

Hello adrian,

What do you think about the Resource Usage view (View / Resource Usage)
where you could insert the Assignment Units field : Insert / Column...

Gérard Ducouret
 