Reporting on Resources' Actual Work

B

Brian

Hi, I'm new to the DB side of MS Project server, so I have a question. If I
wanted to write a query that would return the actual work submitted by all
resources in a given week, which tables would I used? Does the
"AssignmentTimeActualWork" field in the "MSP_VIEW_PROJ_ASSN_TP_BY_DAY" table
store this?

Thanks,
Brian
 
G

Gary L. Chefetz [MVP]

Brian:

I think you'll want to query MSP_Web_Work. You should note that the data
dictionaries for Project and Project Server are located in the help
directory of your Project Server installation. These will provide tremendous
help.
 