I have a project where each main task is a project and there are similar
subtasks under each main task. The main tasks are not linked/dependent
(portfolio of projects so to speak). Resources are assigned to multiple
projects to do the same sort of subtask.
How it is set up:
Main Task 1
-sub task A: Joe
-sub task B: Mary
Main Task 2
-sub task A: Cindy
-sub task B: Mary
Desired report view:
Mary:
-subtask B - Main Task 2....0% complete
-subtask B - Main Task 1 .....100% complete
Not tracking material or costs in this PPM file. I need reporting on "who
is responsible for what and is it done...." ALso, not using % of
resources/hours function. So Mary could be responsible for 50 sub tasks and
we're not managing what % of her is what.
Much obliged for any help!
subtasks under each main task. The main tasks are not linked/dependent
(portfolio of projects so to speak). Resources are assigned to multiple
projects to do the same sort of subtask.
How it is set up:
Main Task 1
-sub task A: Joe
-sub task B: Mary
Main Task 2
-sub task A: Cindy
-sub task B: Mary
Desired report view:
Mary:
-subtask B - Main Task 2....0% complete
-subtask B - Main Task 1 .....100% complete
Not tracking material or costs in this PPM file. I need reporting on "who
is responsible for what and is it done...." ALso, not using % of
resources/hours function. So Mary could be responsible for 50 sub tasks and
we're not managing what % of her is what.
Much obliged for any help!