D
dubosejh
Does anyone know how to view/report on the work value of the
predecessors for a specific task.
I simply want to view the value for work for each of the predecessors
of a task and possible see that added up into something like "total
work for predecessors".
The WBS used represents the Component, Sub component, etc. of a major
piece of software. However, the dependency network spans the tasks
within those Components, sub component, etc., so it is not an option
to created a WBS that matches the predecessor network.
Thanks
predecessors for a specific task.
I simply want to view the value for work for each of the predecessors
of a task and possible see that added up into something like "total
work for predecessors".
The WBS used represents the Component, Sub component, etc. of a major
piece of software. However, the dependency network spans the tasks
within those Components, sub component, etc., so it is not an option
to created a WBS that matches the predecessor network.
Thanks