Problem 1:
I need to evaluate resources on the accuracy of their estimated times.
I would need a report (in Project or excel or Access) which shows me
this:
Resource name Task Estimated time Real time
The way i can print report by resource or for all resources.
Problem 2:
I've used the resource task planning view which shows resource task by
week. But week crossing activities are shown full time on both side.
Example for a 40 hours week:
Week 1
Manage consultants 60hours
Week 2
Manage consultants 60hours
Create table 20 hours
Is there a way to show only the hours left after the week on the new
one?
Thanks all
I need to evaluate resources on the accuracy of their estimated times.
I would need a report (in Project or excel or Access) which shows me
this:
Resource name Task Estimated time Real time
The way i can print report by resource or for all resources.
Problem 2:
I've used the resource task planning view which shows resource task by
week. But week crossing activities are shown full time on both side.
Example for a 40 hours week:
Week 1
Manage consultants 60hours
Week 2
Manage consultants 60hours
Create table 20 hours
Is there a way to show only the hours left after the week on the new
one?