M
Monika Vaccaro
Hello,
I have read through many of the email questions and answers (learned a lot)
but not sure my question is addressed there.
I would like to be able to advance hours on a task in MS Project Pro 2003
(server version) as well as allow the assigned resource to do this via PWA.
The reason we are doing this is that we are bringing existing projects into
the enterprise solution. So, we would like to capture tasks that may have
begun in January 2007 but having the task resources report hours via PWA
beginning July 2007.
Example - I have a task with 80 hours (2 weeks duration), start and finish
dates from 7/16/07 to 7/27/07 and 40 of those hours were accomplished prior
to having the resource use PWA. Resource input the 40 hours via PWA,
beginning 7/23/07 through 7/27/07. In Pro, I saw the 40 hours I accepted but
then the remaining 40 hours are now captured under 7/30, effectively changing
my duration to 6 days as opposed to 10 days. I changed the actual work to 80
hours, hoping to see a 100% complete on the task. Not so. I get 60%
complete because of the actual duration of 6 days.
Is there a simple way we can do this that we can explain to our project
managers as they bring in existing (already in progress) projects?
Thank you so much!
I have read through many of the email questions and answers (learned a lot)
but not sure my question is addressed there.
I would like to be able to advance hours on a task in MS Project Pro 2003
(server version) as well as allow the assigned resource to do this via PWA.
The reason we are doing this is that we are bringing existing projects into
the enterprise solution. So, we would like to capture tasks that may have
begun in January 2007 but having the task resources report hours via PWA
beginning July 2007.
Example - I have a task with 80 hours (2 weeks duration), start and finish
dates from 7/16/07 to 7/27/07 and 40 of those hours were accomplished prior
to having the resource use PWA. Resource input the 40 hours via PWA,
beginning 7/23/07 through 7/27/07. In Pro, I saw the 40 hours I accepted but
then the remaining 40 hours are now captured under 7/30, effectively changing
my duration to 6 days as opposed to 10 days. I changed the actual work to 80
hours, hoping to see a 100% complete on the task. Not so. I get 60%
complete because of the actual duration of 6 days.
Is there a simple way we can do this that we can explain to our project
managers as they bring in existing (already in progress) projects?
Thank you so much!