D
Dyn
Hi Everyone,
Reporting (Project Publish) jobs usually takes about a minute or so before
it completes successfully for most of our projects. But for a couple of our
projects it takes almost about 20 minutes before the Reporting (Project
Publish) job finishes.
Is this a normal behaviour for this job?
I have also noticed in my investigation that the Reporting job for the
project only takes a long time when a least two of the following processes
were intiated for the Project: "Project Save from Project Professional",
"Status Update", "Project Publish".
But when the only job executed is "Project Publish" then the "Reporting
Publish" job takes only a minute or less as expected.
Can anyone please explain to me if this behaviour is normal or not?
Reporting (Project Publish) jobs usually takes about a minute or so before
it completes successfully for most of our projects. But for a couple of our
projects it takes almost about 20 minutes before the Reporting (Project
Publish) job finishes.
Is this a normal behaviour for this job?
I have also noticed in my investigation that the Reporting job for the
project only takes a long time when a least two of the following processes
were intiated for the Project: "Project Save from Project Professional",
"Status Update", "Project Publish".
But when the only job executed is "Project Publish" then the "Reporting
Publish" job takes only a minute or less as expected.
Can anyone please explain to me if this behaviour is normal or not?