G
Gary Zag
yWe have people updating their task status from PWA. This works great if the
can start and work on the task as scheduled. Reporting back when thing don't
go as planned is a different story. If the task is not started on time is
not an issue either. The person selects a new start date and sends it to the
project manager. All good.
Once a task is started and a person is unable to work on the task is where
we are having a reporting problem. If the person changes the finish date
after the task has started it adds additional hours to the tasks which is not
always the case. The person may just not be working on a task for a few days
before he gets back to it. Is there a way to show this from PWA? Similiar
to how you can split a task from Project Pro.
Gary
can start and work on the task as scheduled. Reporting back when thing don't
go as planned is a different story. If the task is not started on time is
not an issue either. The person selects a new start date and sends it to the
project manager. All good.
Once a task is started and a person is unable to work on the task is where
we are having a reporting problem. If the person changes the finish date
after the task has started it adds additional hours to the tasks which is not
always the case. The person may just not be working on a task for a few days
before he gets back to it. Is there a way to show this from PWA? Similiar
to how you can split a task from Project Pro.
Gary