We are experiencing problems when trying to report on Project Costs at a task
level. We can easily sum up task level costs for associates that were
assigned to the task by the PM. However, when the associate self-assigns to
the task through the New Task function, a change occurs with the task ID.
I'm not sure if it's assigning a new task ID and creating a new record, or
changing the existing task ID. Either way, the costs cannot be linked back
to a task name. So, nearly all of our project reports show a blank task at
the top with an associated costs which represents these "self-assigned" task
hours.
Has anyone else experienced this problem, and if so, can you please provide
a recommendation to address it?
Thanks!
Heath
level. We can easily sum up task level costs for associates that were
assigned to the task by the PM. However, when the associate self-assigns to
the task through the New Task function, a change occurs with the task ID.
I'm not sure if it's assigning a new task ID and creating a new record, or
changing the existing task ID. Either way, the costs cannot be linked back
to a task name. So, nearly all of our project reports show a blank task at
the top with an associated costs which represents these "self-assigned" task
hours.
Has anyone else experienced this problem, and if so, can you please provide
a recommendation to address it?
Thanks!
Heath