Z
ziwez0
Hi All,
We are currently evaluating Project Server 2007 and have come up with
a possible show stopper, but hoping this is not the case, we are setup
to report back progress and timesheet.
Scene:
Calendar based upon 8 hour working day, (work in hours and not days)
"Task 1" assigned to me Start: 19-05-2009 :: Finish: 19-05-2009 (no
later than)
Example:
I go to "My Tasks" and select "Task 1"
Total work: 1d
Completed work: 0
Start: 19-05-2009
Finish: 19-05-2009
Remaining work: 8h
I then change Completed work to 12h (press recalculate)
Start: 19-05-2009
Finish: 20-05-2009
Remaining work: 0h
So wait, I worked an additional 4 hours today. but Project Says I will
finish this tomoz.
Right so if i change it to this
Completed work to 12h
Start: 19-05-2009
Finish: 19-05-2009
Remaining work: 0h
and press save, Project will update my task progress and say I
actually did 4 hours on the 18-05-09 and 8 hours on the 19-05-2009,
But what if I have already worked 8 hours that previous day?
I just want to say to project, yes I know my calendar is based on 8
hours but I worked some additional hours today, not yesterday, not
tomorrow, Today!
(obviously i cant change my standard calendar to 12 hours as this
would affect time scales)
Also not sure if there is a tool out there, but would really like to
intergrate progress and timesheet better.
We are currently evaluating Project Server 2007 and have come up with
a possible show stopper, but hoping this is not the case, we are setup
to report back progress and timesheet.
Scene:
Calendar based upon 8 hour working day, (work in hours and not days)
"Task 1" assigned to me Start: 19-05-2009 :: Finish: 19-05-2009 (no
later than)
Example:
I go to "My Tasks" and select "Task 1"
Total work: 1d
Completed work: 0
Start: 19-05-2009
Finish: 19-05-2009
Remaining work: 8h
I then change Completed work to 12h (press recalculate)
Start: 19-05-2009
Finish: 20-05-2009
Remaining work: 0h
So wait, I worked an additional 4 hours today. but Project Says I will
finish this tomoz.
Right so if i change it to this
Completed work to 12h
Start: 19-05-2009
Finish: 19-05-2009
Remaining work: 0h
and press save, Project will update my task progress and say I
actually did 4 hours on the 18-05-09 and 8 hours on the 19-05-2009,
But what if I have already worked 8 hours that previous day?
I just want to say to project, yes I know my calendar is based on 8
hours but I worked some additional hours today, not yesterday, not
tomorrow, Today!
(obviously i cant change my standard calendar to 12 hours as this
would affect time scales)
Also not sure if there is a tool out there, but would really like to
intergrate progress and timesheet better.