Reporting time spend in administrative time

S

Stephane Guerin

We are using the Timesheet in MS Project Server 2007 and I'm trying to build
a report that show the amount of time spend each month on the project and on
the adminitrative tasks. Using Data Anaylis view in the WPA and the
"Timesheet" cube, I've build the Pivot table:
- Row field:
TimeSheet >>> Timesheet Project List Level 02 >>> Timesheet Task List
Level 02
- Column field:
Month
This setup work fine with Project information, but all the task under the
Administrative project are showed as "Auto-Generated". This cause an issue
because I'm not able to differentiate between Working and non-working time.
I'm not able to differentiate work done and holidays.
Is there a way to filter non-working time?

Thank you

Stephane
 
S

Stephane Guerin

Hum, no answer.... This make the Administrative task pretty useless. I
guess this mean I should create a standard project to manage administrative
tasks. This is exactly how we did it on 2003. Disappointing..
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top