S
Stephane Guerin
We are using the Timesheet in MS Project Server 2007 and I'm trying to build
a report that show the amount of time spend each month on the project and on
the adminitrative tasks. Using Data Anaylis view in the WPA and the
"Timesheet" cube, I've build the Pivot table:
- Row field:
TimeSheet >>> Timesheet Project List Level 02 >>> Timesheet Task List
Level 02
- Column field:
Month
This setup work fine with Project information, but all the task under the
Administrative project are showed as "Auto-Generated". This cause an issue
because I'm not able to differentiate between Working and non-working time.
I'm not able to differentiate work done and holidays.
Is there a way to filter non-working time?
Thank you
Stephane
a report that show the amount of time spend each month on the project and on
the adminitrative tasks. Using Data Anaylis view in the WPA and the
"Timesheet" cube, I've build the Pivot table:
- Row field:
TimeSheet >>> Timesheet Project List Level 02 >>> Timesheet Task List
Level 02
- Column field:
Month
This setup work fine with Project information, but all the task under the
Administrative project are showed as "Auto-Generated". This cause an issue
because I'm not able to differentiate between Working and non-working time.
I'm not able to differentiate work done and holidays.
Is there a way to filter non-working time?
Thank you
Stephane