Reporting To Do List or Assignment list

J

jjsb

MSProject 2003. I have tried customizing views, tables and reports but I
still can't seem to create the report that my boss wants. She wants a report
she used to get from an earlier version of Project. Who Does What When and To
do list almost gets there but not quite. Preferably, One page per person
(like you could hand it out to them). By Person, Task, Estimate, Begin and
Start Dates, Predecessors
Thanks!
 
R

Redneck David

So why not creat a table with those fields and put in a page break between
each resource?

Sounds like you are on the right track?

David
 
J

jjsb

How do you tell it to give you a page break between each resource?

Predecessors isn't a field in the drop down when I'm trying to get this type
of To Do list. Is there anyway to get it onto a Resource based report or will
it only display on Task based reports.
 