How do you handle multi project reporting under Project Server? I see very
little reporting in it. Thx.
 
D

Dale Howard [MVP]

Wes --

One default method for multi-project reporting is to navigate to the Project
Center page in PWA and to select one of the views from the Choose a view
pick list. From there, you can apply grouping using one or more of the
fields shown in the current view. Beyond this, you can also export the data
in the current view to Excel by clicking the Export Grid to Excel link in
the lower right corner of the page.

A more powerful method of multi-project reporting involves the use of
Portfolio Analyzer views. Before you can use the Portfolio Analyzer, your
organization would need to define one or more custom enterprise Project
outline codes that will meet your organization's reporting needs for
differentiating between projects. Based on these custom enterprise Project
outline codes, your Project Server administrator can create one or more
custom Portfolio Analyzer views that could meet your multi-project reporting
needs. Hope this helps.
 