J
JP
Hi all,
Using 2003 standard, roughly 30 projects with durations of 6 mo to 8 years,
and a shared resource pool of around 25 (personnel only at this point).
I currently use a customized To Do task list, exported in Excel format, to
mine the following columnar data for each project (from left to right):
Task & Subtask titles
(Current) Task Start & Finish Dates
Baseline Task Start & Finish Dates
Resource Name(s)[percentage of allocation]
Percent Complete (of subtasks as reported by the project manager, and of
major Tasks as calculated by MSP from subtask status data)
I'm looking to add one more column: the percentage complete the task &
subtask SHOULD be as of the status date. Inferred from the baseline as
intersected by the status date? Dunno. Any light shed will be appreciated.
Thanks, JP
Using 2003 standard, roughly 30 projects with durations of 6 mo to 8 years,
and a shared resource pool of around 25 (personnel only at this point).
I currently use a customized To Do task list, exported in Excel format, to
mine the following columnar data for each project (from left to right):
Task & Subtask titles
(Current) Task Start & Finish Dates
Baseline Task Start & Finish Dates
Resource Name(s)[percentage of allocation]
Percent Complete (of subtasks as reported by the project manager, and of
major Tasks as calculated by MSP from subtask status data)
I'm looking to add one more column: the percentage complete the task &
subtask SHOULD be as of the status date. Inferred from the baseline as
intersected by the status date? Dunno. Any light shed will be appreciated.
Thanks, JP