F
Floyd5
Hi,
I'm hoping someone can help. I'm using MS Project as a Programm
Management tool rather than at project level. I.e. each task is in fac
a project. I have developed a simple custom report which orders th
tasks per according to a certain attribute The report displays a
required but these tasks do not make much sense unless the summary tas
is listed against each sub task.
The report currently displays:
Task 1
Task 2
Task 3
However i would like to display
Summary task - task 1
Summary task - task 2
Summary task - task 3
Does anyone know if this is possible?
Thanks is advance
I'm hoping someone can help. I'm using MS Project as a Programm
Management tool rather than at project level. I.e. each task is in fac
a project. I have developed a simple custom report which orders th
tasks per according to a certain attribute The report displays a
required but these tasks do not make much sense unless the summary tas
is listed against each sub task.
The report currently displays:
Task 1
Task 2
Task 3
However i would like to display
Summary task - task 1
Summary task - task 2
Summary task - task 3
Does anyone know if this is possible?
Thanks is advance