I suppose that by forecasted resourcing you mean baseline work. (Forecast
usually referes to the future while actual refers to the past, so there is no
comparison to do in that regard.)
You can do a comparison of baseline work to actual work by resource in the
OLAP Cube.
I'm working on a comparison of baseline work to actual work by resource per
project in OLAP. My question is, how can I compare baseline 1 and baseline 2
with actual work. It's not in the Field List.
I am currently working on this comparison of baseline work to actual work by
resource in the OLAP Cube. I just want to know how to compare baseline 1
work and baseline 2 work to actual work. The field list does not include them.
The data in the OLAP cube is totally currapted due to a bug in MS Project
Server. Wait for Office 12 for this to be fixed. Compate the data you receive
when generating a report on MS Project with one from your OLAP cube.
Ask a Question
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.