Rod Gill

Hi,

You will either need to create a consolidated project but choose not to link
to the sub-projects or create a resource pool. The consolidated project with
no links will have a copy of all tasks and their assignments. It will also
consolidate resource data.
To create a consolidated project:
Create a new file, Select Insert, Project once for each project file you
have. Make sure the Link option is deselected.



--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 
J

Joe

Make sure you are using the resource in a pool file and
all of the projects are using the same resource pool file.
 