Hi,

Some hours have gone into database and some are not

But when I see the report in the project professional i see the all hours of
all days which i have entered .

and some hours which are not gone to the database because when i see the
report through SQL Server Reporting Services .I see there is no any all
hours.

and when I open the project in Project Professional and want to republish
assignments with the option

" OVERWRITE ACTUAL WORK ENTERED BY RESOURCES "

This option is disabled .I don't know how I can activate this option.

Regards

Basim
 
D

Dale Howard [MVP]

Basim --

If you are using Managed Time Periods, this feature is not available. Does
that explain your situation?
 