B
Basim
Hi,
Some hours have gone into database and some are not
But when I see the report in the project professional i see the all hours of
all days which i have entered .
and some hours which are not gone to the database because when i see the
report through SQL Server Reporting Services .I see there is no any all
hours.
and when I open the project in Project Professional and want to republish
assignments with the option
" OVERWRITE ACTUAL WORK ENTERED BY RESOURCES "
This option is disabled .I don't know how I can activate this option.
Regards
Basim
Some hours have gone into database and some are not
But when I see the report in the project professional i see the all hours of
all days which i have entered .
and some hours which are not gone to the database because when i see the
report through SQL Server Reporting Services .I see there is no any all
hours.
and when I open the project in Project Professional and want to republish
assignments with the option
" OVERWRITE ACTUAL WORK ENTERED BY RESOURCES "
This option is disabled .I don't know how I can activate this option.
Regards
Basim