My PM is using MS Project 2003 and has changed a resource name for specific
assigned tasks. I had him republish assignments with the new resource name
for those tasks. This seemed to work ok except for that when he recieves his
daily email notifications stating which tasks are late etc., the original
resource name is showing up attached to that task, not the new assignment.