M
Mel
In Project 2002 standard, tasks that are marked as 100%
complete and with 0 hours remaining are still included in
the Request Progress Information team status sheets when
they are emailed. Why are these completed activities still
being included?
complete and with 0 hours remaining are still included in
the Request Progress Information team status sheets when
they are emailed. Why are these completed activities still
being included?