A
anovak
1. Contractors - we will need to occasionally deal with contractors
that are onsite but only those that are here for large projects and
for a significant amount of time (several weeks or months). My
opinion is that you would just add those folks as individually
enterprise resources for the period of time the project is executed
and then either inactivate them or delete them once completed. If
short term I suppose they could be added as generic resources (Local,
right?)
2. Project Team Site value standardization - Do you see any need to
attempt to standardize the values in Issues, Risks, etc. as far as
priority levels, etc.? I was thinking about trying to learn how to
customize the central Project Team site template to do this as well as
create a standard project management library pre-populated with
artifact forms so that when a new project team site is created, they
will automatically have a full set of PM forms to use (InfoPath,
etc.). On the values for Issues, Risks priorities, categories,
status, etc. do you tend to allow each PM change those values to what
best suites them or standardize?
3. Custom field code descriptions - Do you typically use the
descriptions? Seems like a lot of data entry, especially if concise
but meaningful short names can be developed for the codes.
Thoughts?
Thanks,
Andy Novak
UNT
that are onsite but only those that are here for large projects and
for a significant amount of time (several weeks or months). My
opinion is that you would just add those folks as individually
enterprise resources for the period of time the project is executed
and then either inactivate them or delete them once completed. If
short term I suppose they could be added as generic resources (Local,
right?)
2. Project Team Site value standardization - Do you see any need to
attempt to standardize the values in Issues, Risks, etc. as far as
priority levels, etc.? I was thinking about trying to learn how to
customize the central Project Team site template to do this as well as
create a standard project management library pre-populated with
artifact forms so that when a new project team site is created, they
will automatically have a full set of PM forms to use (InfoPath,
etc.). On the values for Issues, Risks priorities, categories,
status, etc. do you tend to allow each PM change those values to what
best suites them or standardize?
3. Custom field code descriptions - Do you typically use the
descriptions? Seems like a lot of data entry, especially if concise
but meaningful short names can be developed for the codes.
Thoughts?
Thanks,
Andy Novak
UNT