When requesting progress information (Collaborate->Request Progress
Information), the resources from which I am requesting progress information
from get an email notification that looks like this:
QUOTE:
Please update your status on the tasks listed below.
......
To view and respond to the changes, please connect to your Project Web
Access timesheet a
http://<<myServer>>/ProjectServer/Tasks/Taskspage.asp?AllTasks=1&FilterBy=9&GanttView=0.
END QUOTE
The problem is the FilterBy=9. That filter is for "Tasks Pending Manager
Approval", and for some reason, it filters out ALL tasks. So when users
click the link to try to update their tasks, they get a page with no tasks
listed. I need to figure out A) how to remove the filter in the email or B)
why the tasks requesting progress information are not "pending manager
approval".
Thanks for any help!
Ryan
Information), the resources from which I am requesting progress information
from get an email notification that looks like this:
QUOTE:
Please update your status on the tasks listed below.
......
To view and respond to the changes, please connect to your Project Web
Access timesheet a
http://<<myServer>>/ProjectServer/Tasks/Taskspage.asp?AllTasks=1&FilterBy=9&GanttView=0.
END QUOTE
The problem is the FilterBy=9. That filter is for "Tasks Pending Manager
Approval", and for some reason, it filters out ALL tasks. So when users
click the link to try to update their tasks, they get a page with no tasks
listed. I need to figure out A) how to remove the filter in the email or B)
why the tasks requesting progress information are not "pending manager
approval".
Thanks for any help!
Ryan