I am using Microsoft Project 2000. I saved mpp file using Save As option with enabling 'Expand timephased data in database' option in Tools-Options-Save option, as a project database in Sql server
Using Resource Usage View, i am not able to make a query in Sql which will return me specific task, resource & hrs per day
I want to make a query which will return a result like timescaled calendar view appears in Task/Resource Usage View which shows "per day how many hrs a particular resource has worked for a specific task".
Using Resource Usage View, i am not able to make a query in Sql which will return me specific task, resource & hrs per day
I want to make a query which will return a result like timescaled calendar view appears in Task/Resource Usage View which shows "per day how many hrs a particular resource has worked for a specific task".