RES_MAX_UNITS (Enterprise level Resources)

A

Amit

Does anyone know how to convert the RES_MAX_UNITS value to find the actual
avilable resrouce time or unit?

Thanks,
Amit
 
S

Stephen Sanderlin

Calculation of availability is a complicated process that uses
MAX_UNITS, the various calendars, workload, etc. It's not something
that's easily done.



What are you specifically looking to do, and what version are you using?

--

Stephen Sanderlin

Principal Consultant

MSProjectExperts



For Project Server Consulting: http://www.msprojectexperts.com

For Project Server Training: http://www.projectservertraining.com



Read my blog at: http://www.projectserverhelp.com/

Join the community at: http://forums.epmfaq.com
 
A

Amit

I am importing resources to database for simulation purpose. In order to
simulate accurately, I need to know the resources availability. I am using
project server 2007.
 