H
Hadi
Hello Experts,
I like to use the "Reschedule Uncompleted work" command in MS Project but i
have two problems with it.
1- I dont want to reschedule tasks that have already started. I only want
to do so for unstarted tasks (Actual Start = NA)
2- I dont like the fact that Project assigns a constraint for the tasks. is
there a way (probably a macro) that can push the task to the desired
date(data date) by extending its predecessor(s) duration. That is one of the
distinctions between Primavera and microsoft Project. Primavera will not let
you keep an unstarted task in the past.
help is always appreciated.
I like to use the "Reschedule Uncompleted work" command in MS Project but i
have two problems with it.
1- I dont want to reschedule tasks that have already started. I only want
to do so for unstarted tasks (Actual Start = NA)
2- I dont like the fact that Project assigns a constraint for the tasks. is
there a way (probably a macro) that can push the task to the desired
date(data date) by extending its predecessor(s) duration. That is one of the
distinctions between Primavera and microsoft Project. Primavera will not let
you keep an unstarted task in the past.
help is always appreciated.